0.2.2 Overall Goals and
Major Deliverables
System & Installation Issues FE:
Personnel
CFEB hardware/software expert physicist FY04-09 60% OSU
AFEB hardware/software expert, physicist FY04-09 60% CMU
ALCT/TMB electronics/software expert, physicists FY04-09 100
% UCLA
Electronics/Firmware/software engineer FY04 20% FY05-09
40% ?
Tasks
Start: Can start as soon as real LV
system available.
Estimate: 1 months
Start: 3/2003
Estimate CFEB: 6 months
Estimate AFEB: 6 months
Estimate ALCT/TMB: 6 months
Start: Can start 3/2003 but not
realistic until we have real peripheral crates and peripheral crate
electronics, real LV system, and much later RPC’s.
Estimate CFEB: 6 months
Estimate AFEB: 6 months
Estimate ALCT/TMB: 6 months
Start: Procedures can
be started immediately. Final parameters cannot be set
until one has beam in 2007. No real end.
Estimate CFEB/CLCT: 6 months
Estimate AFEB: 6 months
Estimate ALCT/TMB: 6 months
Start: Can start when real
peripheral crate electronics available. Final tuning
needs beam. No real end.
Estimate CFEB/CLCT: 10 months
Estimate AFEB/ALCT: 10 months
Estimate ALCT/TMB: 10 months
Start: 3/2003
Estimate CFEB: 0.5 months
Estimate AFEB: 0.5 months
Estimate ALCT/TMB: 0.5 months
Start:
3/2003. This cannot be finished
until final online-software completed.
No real end.
Estimate CFEB/CLCT: 14 months
Estimate AFEB/ALCT: 14 months
Estimate ALCT/TMB: 14 months
Start:
3/2003. This cannot be finished
until final online-software completed.
Estimate CFEB/CLCT: 18 months
Estimate AFEB/ALCT: 18 months
Estimate ALCT/TMB: 18 months
System & Installation Issues Peripheral Crate:
Personnel
DMB/D360 hardware/software expert physicist FY04-09 40% OSU
ALCT/TMB electronics/software expert, physicists FY04-09 40
% UCLA
CCB electronics/software expert, physicist FY04-09 100% Rice
Electronics/Firmware/software engineer FY04 10% FY05-09
20%
Tasks
Start: Need real VME crates,
VME power supplies and Peripheral Crate
electronics
Estimate: 1 month
Start: Start immediately. For realistic system need real
Peripheral crates and
real Peripheral
Crate electronics.
Estimate DMB/360: 4 months
Estimate ALCT/TMB: 4 months
Estimate CCB: 4 months
Start: Need real Peripheral
Crate Electronics. No real end.
Estimate DMB: 10 months
Estimate ALCT/TMB: 10 months
Estimate CCB: 10 months
Start: Need real peripheral crate electronics. Each board carries
firmware tags.
Estimate DMB: 0.5 months
Estimate ALCT/TMB: 0.5 months
Estimate CCB: 0.5 months
Start: Can start using
prototype Peripheral Crate Electronics. Cannot finish
until we have final online software. Update
over course of experiment.
Estimate DMB: 10 months
Estimate ALCT/TMB: 10 months
Estimate CCB: 10 months
Start: Can start immediately but need final local DAQ software to
finish.
Estimate ALCT/TMB: 24 months
Start: Design can start
once VME crate controllers chosen.
Estimate: 8 months
Start: One needs RPC’s.
Estimate CCB: 24 months
System & Installation Issues Counting House:
Personnel
EMU DAQ/DDU/DCC expert, physicists FY04-FY09 100 % OSU
EMU Trigger
controls expert, physicists FY04-FY09 100 % UCLA
Electronics/Firmware/software engineer FY04 20% FY05-09
40%
Tasks
Start: Need real peripheral crate electronics. Each board carries
firmware tags.
Estimate DAQ: 0.5 months
Estimate Trigger: 0.5 months
Start: When final DDU
boards in hand.
Estimate DDU: 36
Estimate Trigger: 36 months
Start: Need final DDU boards, and TTC system. Final tuning on real
beam.
No end
Estimate DDU: 24 months
Estimate Trigger: 24 months
Start: When local DAQ system operational with no end.
Estimate DDU: 2 months
Estimate Trigger: 2 months
Start: Need real DDU electronics and DDU crate.
Estimate DDU: 24 months
Estimate Trigger: 24 months
Maintenance FE Electronics:
Personnel
Electronics Engineer CFEB FY05-07 50% FY08
37.5% FY09 25% OSU
Electronics Engineer AFEB FY04 8% FY05-FY07 25% FY08 20%
FY09 15% CMU
Electronics Engineer ALCT FY05 30% FY06 60 % FY07 60%
FY08 45%
FY09 30% UCLA
PSL Electronics Engineer LV/LVDB FY04 8% FY05-FY07 15%
FY08 10%
FY09 7% Wisconsin
Electronics Tech FY04-FY09 5% Davis
CERN Technician FY04-FY09 50%
Start: 3/2003 with no end
Estimate CFEB: 21 months
Estimate AFEB: 10 months
Estimate ALCT: 25 months
Estimate LV: 3 months
Estimate LVDB: 1 months
Start: 3/2003
Estimate CFEB: 7 months
Estimate AFEB: 4 months
Estimate ALCT: 10 months
Estimate LV: 1 months
Estimate LVDB: 0.5 months
Start: 3/2003
Estimate CFEB: 5 months
Estimate AFEB: 3 months
Estimate ALCT: 6 months
Estimate LV: 1 months
Estimate LVDB: 0.5 months
Start: 3/2003 , no end.
Estimate CFEB: 1 months
Estimate AFEB: 1 months
Estimate ALCT: 1 months
Estimate LV: 0.5 months
Start: 3/2003 , no end.
Estimate CFEB: 3.5 months
Estimate AFEB: 3 months
Estimate ALCT: 3 months
Estimate LV: 2 months
Estimate LVDB: 0.5
months
Personnel
Electronics Engineer DMB/D360 FY05-07 30% FY08 22.5% FY09 15%
OSU
Electronics Engineer TMB FY05 40% FY06 40 % FY07 40% FY08 30%
FY09 20% UCLA
Electronics Engineer FY04 8% FY05-FY07 50% FY08 40% FY09 25%
Rice
CERN Technician FY04-FY09 30%
Start: Requires VME crates and peripheral crate
electronics. No end.
Estimate DMB/VME controller: 11
months
Estimate CLCT: 12 months
Estimate CCB/VME Crate: 12 months
Start: Requires VME crates and peripheral crate
electronics.
Estimate DMB/VME controller: 6
months
Estimate CLCT: 7 months
Estimate CCB: 6 months
Start: Requires VME crates and peripheral crate
electronics.
Estimate DMB/VME controller: 1
months
Estimate CLCT: 1 months
Estimate CCB: 1 months
Start: Requires VME crates and peripheral crate
electronics. No end.
Estimate DMB/VME controller: 1
months
Estimate CLCT: 1 months
Estimate CCB: 1 months
Start: Requires VME crates and peripheral crate
electronics. No end.
Estimate DMB/VME controller: 2
months
Estimate CLCT: 2 months
Estimate CCB: 2 months
Start: Requires TTC System,VME crates and
peripheral crate electronics.
No end.
Estimate CCB: 9 months
Start: Requires VME crates and peripheral crate
electronics. No end.
Estimate DMB/VME controller: 1
months
Start: Requires VME crates and peripheral crate
electronics. No end.
Estimate DMB/VME controller: 3
months
Personnel
Electronics Engineer DDU/DCC FY05-07 20% FY08 15% FY09 10%
OSU
CERN Technician FY04-FY09 20%
Post Doc FY04-FY09 100% UCD
Start: Requires VME crate and DDU/DDC
electronics. No end.
Estimate
DDU/DCC controller: 14 months
Start: Requires Linux DDU computer. No end.
Estimate DDU/DCC controller: 4
months
Start: Requires Linux local DAQ computers. No end.
Estimate Gigabit card and driver: 2
months
Estimate Service and Repair: 36 months
Start: Requires Linux local DAQ computers. No end.
Estimate Service and Repair: 36 months
Start: Requires final DDU boards. No end.
Estimate
optical links: 4 months
Start: 3/2003
Estimate: 2 months