0.2.2 Overall Goals and Major Deliverables

 

   System & Installation Issues FE:

 

       Personnel

       CFEB hardware/software expert  physicist FY04-09 60% OSU

       AFEB hardware/software expert, physicist  FY04-09 60% CMU

       ALCT/TMB electronics/software expert, physicists FY04-09 100 % UCLA

       Electronics/Firmware/software engineer FY04 20% FY05-09 40%  ?

 

       Tasks

   Start: Can start as soon as real LV system available.

   Estimate:   1 months

   Start:  3/2003

   Estimate CFEB: 6 months

   Estimate AFEB:  6 months

   Estimate ALCT/TMB: 6 months

   Start: Can start 3/2003 but not realistic until we have real peripheral crates and peripheral crate electronics, real LV system, and much later RPC’s.

   Estimate CFEB: 6 months

   Estimate AFEB:  6 months

   Estimate ALCT/TMB: 6 months

          Start: Procedures can be started immediately. Final parameters cannot be set

             until one has beam in 2007. No real end.

          Estimate CFEB/CLCT:  6 months

    Estimate AFEB:  6  months

    Estimate ALCT/TMB: 6 months

          Start: Can start when real peripheral crate electronics available. Final tuning

             needs beam. No real end.

          Estimate CFEB/CLCT:  10 months

    Estimate AFEB/ALCT:  10  months

    Estimate ALCT/TMB: 10 months

          Start: 3/2003

          Estimate CFEB:  0.5 months

    Estimate AFEB:  0.5 months

    Estimate ALCT/TMB: 0.5 months

 

    Start:  3/2003. This cannot be finished until final online-software completed.

        No real end.

          Estimate CFEB/CLCT:  14 months

    Estimate AFEB/ALCT:  14  months

    Estimate ALCT/TMB: 14 months

    Start:  3/2003. This cannot be finished until final online-software completed.

          Estimate CFEB/CLCT:  18 months

    Estimate AFEB/ALCT:  18  months

    Estimate ALCT/TMB: 18 months

 

 

    System & Installation Issues Peripheral Crate:

 

       Personnel

       DMB/D360 hardware/software expert  physicist FY04-09 40% OSU

       ALCT/TMB electronics/software expert, physicists FY04-09 40 % UCLA

       CCB electronics/software expert, physicist FY04-09 100% Rice

       Electronics/Firmware/software engineer FY04 10% FY05-09 20% 

 

 

      Tasks

           Start: Need real VME crates, VME power supplies and Peripheral Crate

                electronics

          Estimate: 1 month

           Start: Start immediately. For realistic system need real Peripheral crates and

                real Peripheral Crate electronics.

     Estimate DMB/360: 4 months

     Estimate ALCT/TMB: 4 months

     Estimate CCB: 4 months

           Start: Need real Peripheral Crate Electronics. No real end.

     Estimate DMB: 10 months

     Estimate ALCT/TMB: 10 months

     Estimate CCB: 10 months

            Start: Need real peripheral crate electronics. Each board carries firmware tags.

     Estimate DMB: 0.5 months

     Estimate ALCT/TMB: 0.5 months

     Estimate CCB: 0.5 months

           Start: Can start using prototype Peripheral Crate Electronics. Cannot finish

            until we have final online software. Update over course of experiment.

     Estimate DMB: 10 months

     Estimate ALCT/TMB: 10 months

     Estimate CCB: 10 months

             Start: Can start immediately but need final local DAQ software to finish.

      Estimate ALCT/TMB: 24 months

            Start: Design can start once VME crate controllers chosen.

            Estimate: 8 months

           Start: One needs RPC’s.

     Estimate CCB: 24 months

 

 

    System & Installation Issues Counting House:

 

         Personnel

         EMU DAQ/DDU/DCC expert, physicists FY04-FY09 100 % OSU

         EMU Trigger controls expert, physicists FY04-FY09 100 % UCLA

         Electronics/Firmware/software engineer FY04 20% FY05-09 40% 

 

         Tasks

            Start: Need real peripheral crate electronics. Each board carries firmware tags.

     Estimate DAQ: 0.5 months

     Estimate Trigger: 0.5 months

            Start:  When final DDU boards in hand.

     Estimate DDU: 36

     Estimate Trigger: 36 months

            Start: Need final DDU boards, and TTC system. Final tuning on real beam.

            No end

     Estimate DDU: 24 months

     Estimate Trigger: 24 months

            Start: When local DAQ system operational with no end.

     Estimate DDU: 2 months

     Estimate Trigger: 2 months

            Start: Need real DDU electronics and DDU crate.

     Estimate DDU: 24 months

     Estimate Trigger: 24 months

 

 

   Maintenance FE Electronics:

 

          Personnel

          Electronics Engineer CFEB FY05-07 50% FY08 37.5% FY09 25% OSU

          Electronics Engineer AFEB FY04 8% FY05-FY07 25% FY08 20%

                                                                                                 FY09 15% CMU

          Electronics Engineer ALCT FY05 30% FY06 60 % FY07 60% FY08 45%

                                                                                                 FY09 30% UCLA

          PSL Electronics Engineer LV/LVDB FY04 8% FY05-FY07 15% FY08 10%

                                                                                                 FY09 7%   Wisconsin

          Electronics Tech FY04-FY09 5% Davis

         CERN Technician FY04-FY09 50%

 

 

            Start:  3/2003 with no end

     Estimate CFEB: 21 months

     Estimate AFEB:   10 months

     Estimate ALCT: 25 months

     Estimate LV:   3 months

     Estimate LVDB:   1 months

            Start:  3/2003

     Estimate CFEB: 7 months

     Estimate AFEB:   4 months

     Estimate ALCT: 10 months

     Estimate LV:   1 months

     Estimate LVDB:   0.5 months

            Start:  3/2003

     Estimate CFEB: 5 months

     Estimate AFEB:   3 months

     Estimate ALCT: 6 months

     Estimate LV:   1 months

     Estimate LVDB:   0.5 months

            Start:  3/2003 , no end.

     Estimate CFEB: 1 months

     Estimate AFEB:   1 months

     Estimate ALCT: 1 months

     Estimate LV:   0.5 months

           Start:  3/2003 , no end.

     Estimate CFEB: 3.5 months

     Estimate AFEB:   3 months

     Estimate ALCT: 3 months

     Estimate LV:   2 months

     Estimate LVDB:   0.5 months

 

 

Maintenance Peripheral Crate Electronics

 

       Personnel

      Electronics Engineer DMB/D360 FY05-07 30% FY08 22.5% FY09 15% OSU

      Electronics Engineer TMB FY05 40% FY06 40 % FY07 40% FY08 30%

                                                                                                  FY09 20% UCLA

      Electronics Engineer FY04 8% FY05-FY07 50% FY08 40% FY09 25% Rice

      CERN Technician FY04-FY09 30%

 

 

            Start:  Requires VME crates and peripheral crate electronics. No end.

     Estimate DMB/VME controller: 11 months

     Estimate CLCT:   12 months

     Estimate CCB/VME Crate: 12 months

            Start:  Requires VME crates and peripheral crate electronics. 

     Estimate DMB/VME controller: 6 months

     Estimate CLCT:   7 months

     Estimate CCB: 6 months

            Start:  Requires VME crates and peripheral crate electronics. 

     Estimate DMB/VME controller: 1 months

     Estimate CLCT:   1 months

     Estimate CCB: 1 months

            Start:  Requires VME crates and peripheral crate electronics. No end.

     Estimate DMB/VME controller: 1 months

     Estimate CLCT:   1 months

     Estimate CCB: 1 months

            Start:  Requires VME crates and peripheral crate electronics. No end.

     Estimate DMB/VME controller: 2 months

     Estimate CLCT:   2 months

     Estimate CCB: 2 months

            Start:  Requires TTC System,VME crates and peripheral crate electronics.

            No end.

     Estimate CCB: 9 months

            Start:  Requires VME crates and peripheral crate electronics. No end.

     Estimate DMB/VME controller: 1 months

            Start:  Requires VME crates and peripheral crate electronics. No end.

     Estimate DMB/VME controller: 3 months

 

 

Maintenance Counting House Electronics

 

      Personnel

      Electronics Engineer DDU/DCC FY05-07 20% FY08 15% FY09 10% OSU

      CERN Technician FY04-FY09 20%

      Post Doc FY04-FY09 100% UCD

 

 

            Start:  Requires VME crate and DDU/DDC electronics. No end.

     Estimate DDU/DCC controller: 14 months

           Start:  Requires Linux DDU computer. No end.

     Estimate DDU/DCC controller: 4 months

           Start:  Requires Linux local DAQ computers. No end.

     Estimate Gigabit card and driver: 2 months

           Estimate Service and Repair: 36 months

           Start:  Requires Linux local DAQ computers. No end.

           Estimate Service and Repair: 36 months

            Start:  Requires final DDU boards. No end.

                  Estimate optical links: 4 months

 

Bookkeeping

 

           Start:  3/2003

           Estimate:  2 months