0.2 FEE Integration and
Maintenance
0.2.1 Expected Deliverables
from the Project
- Production
On Chamber Electronics Boards with operational firmware, and cables.
Boards: CFEB, AFEB, ALCT, LVDB, LVMB
Cables: CSC-CFEB CSC-AFEB AFEB-ALCT
- Production
Peripheral Crate Boards with operational firmware, and cables.
Boards: DMB,TMB,CCB,RIM(Rpc
interface module)
Cables: CFEB-DMB CFEB-TMB
LVMB-DMB RPC-RIM
ALCT-TMB LVDB-CFEB
LVDB-ALCT
Fiber: CCB-TTC TMB-Trigger
- Peripheral
VME Crates with custom back-planes, power, cooling, magnetic shielding,
with external interface for monitoring and controlling voltages.
Crate
controller for interfacing DCS to VME boards.
Boards: VME Crate Controller
Fiber: Ethernet
- Production
Counting House Boards with operational firmware.
Boards: DDU, DCC
Fiber: DAQMB-DDU
- Counting
House VME Crates with back-planes, power, cooling, and external interface
for monitoring and controlling voltages. Crate controller for interfacing
DCS to DDU boards.
Boards: VME Crate Controller
(Bit3)
- Local DAQ Computer Farm (surface or counting house)
with gigabit ethernet PCI card.
Fiber: DDU-PC
- DCS
computer with interface card to Peripheral crate VME controller and
interface card to Local Trigger Controller board.
Cable: ethernet-VME controller,
additional hubs and switches envisioned,
coax connection to LTC
- Accounting
of cables, including optical fiber, and spares. Cable data base accounting
for delivered cables. Testers for Skew Clear cables are available at CERN.
- Accounting
for electronics boards and spare boards. Accounting for spare components
for each board. Equipment data base accounting for delivered electronics
boards including repair history.
0.2.2 Overall Goals and
Major Deliverables
System & Installation Issues FE:
- Develop
power on/off procedures
- Address
system integration issues
- Address
noise and ground loop issues
- Determine optimal AFEB thresholds, CFEB
trigger primitive thresholds and trigger mode
- Develop
methods to time in electronics, Determine optimal timing constants.
- Setup
procedures for tracking and modify firmware.
- Develop
beam off software for monitoring and diagnosing AFEB, CFEB, ALCT defining
performance parameters and standards
- Develop
spy data monitoring software
System & Installation Issues Peripheral Crate:
- Develop
VME crate power on/off procedures
- Address
system integration issues
- Develop
methods to time in electronics, Determine optimal timing constants
- Setup
procedures for tracking and modify firmware.
- Develop
beam off software for monitor and diagnosing CLCT, CCB, and DMB defining
performance parameters and standards.
- Develop
spy data software which emulates ALCT/CLCT triggers to monitor trigger
electronics performance.
- Setup
ethernet web (switches, hubs,…) for VME crate controllers.
- Integrate
RPC’s into CLCT trigger
System & Installation Issues Counting House:
- Set
up procedures for tracking and modifying firmware.
- Develop
error monitoring software to track buffer overflows and communication
errors.
- Develop
SEU reset and monitoring procedures.
- Determine
scaling of spy data.
- Develop
software to monitor trigger rates.
Maintenance FE Electronics:
- Organize
and provide service to AFEB, CFEB, LVDB, LVMB, and ALCT and FE cables on
disks
- Develop
test stand to debug AFEB, CFEB, LVDB, LVMB, and ALCT boards (CERN or USA)
and FE cables.
- Set
up equipment for fixing boards, chip replacement,… (CERN or USA)
- Maintain
CERN stockroom for FEE replacement boards and replacement cables
- Maintain
stock of replacement chips for board repair (CERN or USA)
Maintenance Peripheral Crate Electronics
- Organize
and provide service to VME crate, VME Controller, CLCT, CCB, and DMB and
peripheral crate cables on disks
- Develop
test stand to debug VME Controller, CLCT, CCB, and DMB boards (CERN or
USA)
- Set
up equipment for fixing boards, chip replacement,… (CERN or USA)
- Maintain
CERN stockroom for peripheral crate replacement boards and replacement
cables
- Maintain
stock of replacement chips for board repair (CERN or USA
- Service
and repair CCB interface to TTC system.
- Service
and repair VME controller ethernet system (ethernet hubs, ethernet
switches)
- Service
and repair of Linux slow control computer. Maintain low level driver to
VME controller.
Maintenance Counting House Electronics
- Provide service to VME crate, VME controller, DDU and DCC
boards.
- Service and repair Linux DDU control computer.
- Service and repair 18 Linux PC computers. Maintain low level
gigabit ethernet driver.
- System management of local computers. Software upgrades,
backup, data-storage, account management.
- Service and repair optical fiber links.
Bookkeeping
- Coordinate “geographical” nomenclature for FE, Peripheral
crate, and Counting house electronics. Maintain map between board and
geographical address.
0.2.3 Major Milestones
- FEE and VME Geographical Configuration 3/1/03
- System Integration and Noise Issues at CERN(Start) 3/1/03
- Procedures for Firmware Modification /tracking 6/1/03
- System Integration and Noise Issues at CERN(End) 1/1/06
- First Version of FEE Diagnostic & Calibration Software 1/1/03
- Final FEE Diagnostic & Calibration Software 6/1/05
- First Version of VME Diagnostic & Calibration Software
1/1/03
- Final Version of VME Diagnostic & Calibration Software
1/1/06
- First Version of DAQ/DDU Diagnostic & Calibration
Software 1/1/04
- Final Version of DAQ/DDU Diagnostic & Calibration
Software 6/1/06